Kansas City International Airport (MCI)
Kansas City, MO
New Terminal BHS Project
Project Highlights:
- 3+ Miles of conveying equipment
- 100% TSA submittal approval rate
- Project was on time and on budget
Project Description:
The Kansas City Aviation Department (KCAD) designed and constructed a new terminal at Kansas City International Airport (MCI) to replace existing Terminals A, B, and C. The new terminal processes and houses all terminal operations for all outbound and inbound flights at MCI.
As a member of the BHS/CBIS Design-Build (DB) team, Studdiford Technical Solutions, LLC (STS) provided BHS and TSA subject matter expertise and design oversight for the new terminal, a greenfield site comprising inbound, outbound, FIS, and transfer BHS. The scope of services included oversight of all BHS CBIS design for TSA compliance and TSA submittal preparation, including:
- BHS designer/OEM support to ensure TSA PGDS CBIS design and submittal compliance
- Development of the Basis of Design Report (BDR)
- Flight Schedule Analysis and verification
- Development of TSA Requests For Variance (RFVs)
- Development of Contingency and Configuration Management Plans
- Development of Life Cycle Cost Analysis (LCCA)
- Review of all TSA submittal documentation
- Participation and insight in design team meetings
The team’s participation has resulted in a 100% TSA submittal approval rate.
“Speaking for all of us here at VI: We are glad to have you (Ryan Crews) and all your team helping us all our projects. We could not do it without you!”
Benjamin T. Barnett, P.E.
Engineering Project Manager, Vanderlande Industries, 2020